Polihali project delayed to 2027

- Advertisement -
- Advertisement -

The long-delayed M37 billion Lesotho Highlands Water Project (LHWP) – facing funding pressures, COVID-19 delays and protests – will begin water delivery in 2027.

Responding to questions from Reuters, the RSA Department of Water and Sanitation said the building of roads, accommodation and electricity installations had begun, and that border closures due to COVID-19 would not have a “material impact”.

“COVID-19 disruptions aren’t expected to have a material impact on the planned completion date of project works and commencement date of water delivery to South Africa, in early 2027.”

Created in 1984, the LHWP was designed to have five phases over 30 years and transfer up to 2 billion cubic meters of water annually from Lesotho to South Africa’s commercial hubs and industries like Sasol and Eskom.

Phase one started delivering water in 1996. Phase two, which includes the 2.3 billion cubic metre Polahli Dam and a 1,200 megawatt hydro-electric plant in Lesotho, was meant to be complete by 2020.

The department said the 60 billion rand needed by the Trans-Caledon Tunnel Authority (TCTA), South Africa’s state-owned company responsible for the Lesotho project, would be generated through further debt issuance.

“TCTA is planning a debt capital markets programme in the near future to complement funding of capital expenditure and possible long-term refinancing of shorter-dated maturities,” the department said.

In 2019 and 2020 water supply to Gauteng was periodically throttled as a result of severe drought related to climate change and creaking infrastructure due to funding shortfalls for maintenance and new projects.

Bitter disagreements over compensation and job reservations between Lesotho officials and the communities that need to be relocated to make way for construction, around 500 households in 35 villages, led to protests in January and February, threatening to lengthen delays.

Two Lesotho community organisations told Reuters they were considering further protests and legal action against the Lesotho Highlands Development Authority (LHDA). The LHDA did not respond to written questions from Reuters. (Reporting by Mfuneko Toyana; editing by Jonathan Oatis)

-Reuters

- Advertisement -

Hot this week

Training for dairy farmers

The Lesotho National Dairy Board is inviting dairy farmers...

Lesotho growth steady amid uncertainty

Global growth has showed moderate progress in 2025 although...

Academy nurtures young talent

Local performing artist Rethabile Likoche wears many hats. He...

Enduring Sefako sa Menoaneng celebrates 25 years

Renowned veteran famo artist Lebohang Letṧohla, better known as...

Polihali Bargaining Forum launched 

The Polihali Bargaining Forum was officially launched yesterday at...

Topics

Training for dairy farmers

The Lesotho National Dairy Board is inviting dairy farmers...

Lesotho growth steady amid uncertainty

Global growth has showed moderate progress in 2025 although...

Academy nurtures young talent

Local performing artist Rethabile Likoche wears many hats. He...

Enduring Sefako sa Menoaneng celebrates 25 years

Renowned veteran famo artist Lebohang Letṧohla, better known as...

Polihali Bargaining Forum launched 

The Polihali Bargaining Forum was officially launched yesterday at...

Outgoing AUC chairperson hails Lesotho 

The chairperson of the African Union Commission (AUC), Moussa...

US aid freeze won’t affect availability of ARVs

Health minister, Selibe Mochoboroane has reassured the nation that...

LHDA launches bargaining forum

The Lesotho Highlands Development Authority (LHDA) will tomorrow launch...
spot_imgspot_imgspot_imgspot_img

Related Articles

Popular Categories

spot_imgspot_imgspot_imgspot_img
0
Would love your thoughts, please comment.x
()
x